1. Home
  2. AACE International
  3. AACE-PSP Dumps

Reasons to Choose Our AACE International AACE-PSP Exam Dumps

AACE International AACE-PSP Exam Dumps - Curated by Subject Matter Experts

Are you tired of getting AACE International AACE-PSP dumps with wrong answers? Don’t worry now because our Planning & Scheduling Professional (PSP) Exam dumps are curated by subject matter experts ensuring every question has the right answer

Prepare Your Exam with AACE International AACE-PSP Dumps on Any Device

We facilitate you by offering our AACE International AACE-PSP exam dumps in three different formats (PDF file, Offline, and Online Practice Test Software)

Self-Assess Your PSP Certification Exam Preparation

Self-Assess Your AACE International AACE-PSP exam preparation with our AACE-PSP dumps enriched with various features such as time limit, personalized result page, etc

AACE-PSP Dumps

Eliminate Risk of Failure with AACE International AACE-PSP Exam Dumps

Schedule your time wisely to provide yourself sufficient time each day to prepare for the AACE International AACE-PSP exam. Make time each day to study in a quiet place, as you'll need to thoroughly cover the material for the Planning & Scheduling Professional (PSP) Exam . Our actual PSP Certification exam dumps help you in your preparation. Prepare for the AACE International AACE-PSP exam with our AACE-PSP dumps every day if you want to succeed on your first try.

Q1.

Assuming that you had only one crane capable of 30 lifts per day, 3 column pours requiring 28 lifts each, plus associated assorted work requiring an additional 150 lifts, what is the minimum planned working duration for this work?

q1_AACE-PSP

Answer: A
Q2.

Assuming a total of 30 lifts per crane per day, what is the maximum number of lifts that could be accomplished using 3 small tower cranes over a 5-day period?

q2_AACE-PSP

Answer: A
Q3.

There is only enough room for a maximum of 4 cranes to be placed on-site. Assuming that a single crane can perform 35 lifts per day and that a column pour requires 60 lifts, what is the minimum number of tower cranes that should be used for the above described column pours?

q3_AACE-PSP

Answer: A
Q4.

Each column must be poured in one day. Each column requires 2,000 cubic feet of concrete. The lift bucket has a capacity of 40 cubic feet. How many lifts will be required per column pour?

q4_AACE-PSP

Answer: B
Q5.

Crane operators require 1 hour prep and 1 hour clean-up and inspection per day. There is only 1 crane operator allocated per crane. Crane operators are not allowed to work more than 8 hours a day. Lunchtime break lasts 1 hour. Assuming a 10 minute cycle time, how many lifts per day can be expected?

q5_AACE-PSP

Answer: A

Are You Looking for More Updated and Actual AACE International AACE-PSP Exam Questions?

If you want a more premium set of actual AACE International AACE-PSP Exam Questions then you can get them at the most affordable price. Premium PSP Certification exam questions are based on the official syllabus of the AACE International AACE-PSP exam. They also have a high probability of coming up in the actual Planning & Scheduling Professional (PSP) Exam .
You will also get free updates for 90 days with our premium AACE International AACE-PSP exam. If there is a change in the syllabus of AACE International AACE-PSP exam our subject matter experts always update it accordingly.